9 min read ยท Updated
How to Read an Air Balance Report
An air balance report can run to hundreds of pages of tables, and most of the people who receive one are not balancing technicians. Owners, facility managers, general contractors, and engineers all need to know the same thing: does this building deliver the air it was designed to deliver? This guide walks through a typical report in the order the pages appear and points out the numbers that answer that question.
๐ Formats vary
The Front Matter
Before any data, a report should establish who did the work and with what.
- Certification page. The firm, its certifying body and certification number, the project, and the signature or stamp of the certified professional responsible.
- Instrument list. Every instrument used, with its serial number and last calibration date. Certifying bodies require calibration at set intervals, commonly twelve months. An instrument out of calibration on the test date undermines every reading taken with it.
- Summary and deficiency list. A plain-language account of what was balanced and a list of everything that could not be brought to design, with the reason. This is the most useful page in the report and the one to read first.
Fan Data Sheets
Each air handler, rooftop unit, and exhaust fan gets a sheet comparing design with actual. The left column comes from the equipment schedule and the submittals. The right column is what the technician found.
| Line | What it tells you |
|---|---|
| Total CFM, design and actual | Whether the fan as a whole is moving the right amount of air. If this is low, no terminal adjustment can fix it. |
| Outside air CFM | Whether the building is getting its ventilation air. Often the most consequential line on the sheet and the one most often missed. |
| Fan RPM | The speed the fan was left at. A change from the submittal value means sheaves or drive settings were altered to reach design. |
| Static pressures | Suction, discharge, and total or external static pressure. Compared with design, they show whether the duct system has more or less resistance than the engineer assumed. |
| Motor nameplate HP, volts, and full-load amps | The motor's limits. |
| Actual volts and amps | The motor's present load. Actual amps above nameplate full-load amps means the motor is overloaded. |
| Sheaves and belts | Sizes as left, so the drive can be restored after maintenance. |
Read the amps and the static pressure together. A fan at design airflow with static pressure well above design is working against a restrictive duct system, and it is probably drawing close to full-load amps to do it. That system has no margin left for filters to load up.
Outlet Sheets
These are the long tables, one line per diffuser, grille, or register:
- Room and terminal number, matching the tags on the mechanical drawings
- Terminal type and size, and the correction factor used if the reading needed one
- Design CFM from the drawings
- Preliminary CFM, before adjustment, in reports that include it
- Final CFM, after adjustment
- Percent of design, final divided by design
Scan the percent column. Specifications most commonly accept 90% to 110% for individual terminals, with tighter limits for critical spaces. Then look at the pattern, not only the individual lines:
- A few terminals out, the rest fine. Local problems: a blocked diffuser, a crushed flex duct, a missing damper. Each should appear on the deficiency list.
- Everything a little low. The fan is short of air. Look back at the fan sheet for the reason.
- Terminals at the end of a branch low, those at the start high. The branch was not proportionally balanced, or its duct is undersized.
The Air Balance Report Builder reproduces this table and does the percentage arithmetic, which is a quick way to check a line that looks wrong.
Traverse Sheets
Where airflow was measured inside a duct with a pitot tube, the report includes the traverse: duct size, cross-sectional area, a grid of velocity or velocity pressure readings, the average velocity, and the resulting CFM. Traverses are how fan totals, outside air quantities, and main branch flows are established.
Two things are worth checking. The duct dimensions should be inside dimensions, net of any liner. And the grid should have a sensible number of points for the duct size, with readings that vary smoothly. A grid in which every reading is identical was not measured.
Terminal Unit Sheets
In variable air volume systems, each VAV box has its own line or sheet: inlet size, design maximum and minimum airflow, the measured airflow at each, the airflow the building automation system displayed at the same time, and the calibration constant left in the controller. The measured and displayed values should agree closely. If they do not, the controls will be regulating to the wrong number for the life of the building.
What Belongs on the Deficiency List
A good report is candid about what could not be achieved. Typical entries:
- Fan at maximum speed or motor at full-load amps, total airflow below design
- Terminals that cannot reach design with dampers fully open
- Missing or inaccessible volume dampers
- Duct leakage evident from the gap between fan total and outlet total
- Controls not complete, so a mode could not be tested
- Outside air damper or economizer not operating
An empty deficiency list on a large project is not a sign of a perfect building. It is a reason to ask how the work was done.
Red Flags
- Every reading at or very near 100% of design. Real systems scatter across the tolerance band.
- No preliminary readings and no remarks. There is no evidence of what was adjusted.
- Design values that do not match the drawings. The report may have been built from an outdated set.
- Outlet total greater than the fan total. Air cannot be created in the ductwork. One of the two measurements is wrong.
- Actual amps above full-load amps with no comment.
- Terminals marked "not accessible" or "N/A" in spaces that matter.
- Instrument calibration dates that are missing or expired.
- No outside air measurement on a system that brings in ventilation air.
What the Report Does Not Tell You
A balance report is a snapshot of airflow in one operating mode on the day of testing. It does not show that the controls sequence works, that temperatures hold under load, or that the building will stay balanced after filters load and tenants rearrange partitions. Those questions belong to commissioning and to ongoing maintenance. What the report does provide is the baseline: the numbers every later measurement gets compared against.
FAQ
What is an air balance report?+
What does the percent of design column mean?+
Why is the fan airflow higher than the sum of the outlets?+
What is the difference between preliminary and final readings?+
Who signs an air balance report?+
How long should an air balance report be kept?+
Related Guides
Air Balance Report Builder
Fill in a report sheet and export it as PDF or CSV
Air Balance Report Template
The core report fields with a completed example
TAB Procedure: Step by Step
The work that produces the numbers in the report
TAB vs. Commissioning
How the report is used in the commissioning process