An air balance report can run to hundreds of pages of tables, and most of the people who receive one are not balancing technicians. Owners, facility managers, general contractors, and engineers all need to know the same thing: does this building deliver the air it was designed to deliver? This guide walks through a typical report in the order the pages appear and points out the numbers that answer that question.

๐Ÿ“ Formats vary

NEBB, AABC, and TABB each publish their own report forms, and every firm lays its pages out a little differently. The content described here is common to all of them.

The Front Matter

Before any data, a report should establish who did the work and with what.

Fan Data Sheets

Each air handler, rooftop unit, and exhaust fan gets a sheet comparing design with actual. The left column comes from the equipment schedule and the submittals. The right column is what the technician found.

Line What it tells you
Total CFM, design and actual Whether the fan as a whole is moving the right amount of air. If this is low, no terminal adjustment can fix it.
Outside air CFM Whether the building is getting its ventilation air. Often the most consequential line on the sheet and the one most often missed.
Fan RPM The speed the fan was left at. A change from the submittal value means sheaves or drive settings were altered to reach design.
Static pressures Suction, discharge, and total or external static pressure. Compared with design, they show whether the duct system has more or less resistance than the engineer assumed.
Motor nameplate HP, volts, and full-load amps The motor's limits.
Actual volts and amps The motor's present load. Actual amps above nameplate full-load amps means the motor is overloaded.
Sheaves and belts Sizes as left, so the drive can be restored after maintenance.

Read the amps and the static pressure together. A fan at design airflow with static pressure well above design is working against a restrictive duct system, and it is probably drawing close to full-load amps to do it. That system has no margin left for filters to load up.

Outlet Sheets

These are the long tables, one line per diffuser, grille, or register:

Scan the percent column. Specifications most commonly accept 90% to 110% for individual terminals, with tighter limits for critical spaces. Then look at the pattern, not only the individual lines:

The Air Balance Report Builder reproduces this table and does the percentage arithmetic, which is a quick way to check a line that looks wrong.

Traverse Sheets

Where airflow was measured inside a duct with a pitot tube, the report includes the traverse: duct size, cross-sectional area, a grid of velocity or velocity pressure readings, the average velocity, and the resulting CFM. Traverses are how fan totals, outside air quantities, and main branch flows are established.

Two things are worth checking. The duct dimensions should be inside dimensions, net of any liner. And the grid should have a sensible number of points for the duct size, with readings that vary smoothly. A grid in which every reading is identical was not measured.

Terminal Unit Sheets

In variable air volume systems, each VAV box has its own line or sheet: inlet size, design maximum and minimum airflow, the measured airflow at each, the airflow the building automation system displayed at the same time, and the calibration constant left in the controller. The measured and displayed values should agree closely. If they do not, the controls will be regulating to the wrong number for the life of the building.

What Belongs on the Deficiency List

A good report is candid about what could not be achieved. Typical entries:

An empty deficiency list on a large project is not a sign of a perfect building. It is a reason to ask how the work was done.

Red Flags

What the Report Does Not Tell You

A balance report is a snapshot of airflow in one operating mode on the day of testing. It does not show that the controls sequence works, that temperatures hold under load, or that the building will stay balanced after filters load and tenants rearrange partitions. Those questions belong to commissioning and to ongoing maintenance. What the report does provide is the baseline: the numbers every later measurement gets compared against.

FAQ

What is an air balance report?+
An air balance report is the written record of a Testing, Adjusting, and Balancing (TAB) job. It lists the design airflow for every fan and every air terminal in a building, the airflow actually measured after adjustment, and the operating data of the equipment. Its purpose is to show whether the HVAC system delivers the airflow the mechanical design called for.
What does the percent of design column mean?+
It is measured airflow divided by design airflow. A diffuser designed for 200 CFM that measures 190 CFM is at 95% of design, which some reports show instead as a variance of โˆ’5%. Specifications most often accept individual terminals between 90% and 110% of design.
Why is the fan airflow higher than the sum of the outlets?+
Because ductwork leaks. The fan total, measured by duct traverse near the unit, includes air that escapes through seams and joints before it reaches a terminal. A difference of a few percent is ordinary. A difference above roughly ten percent suggests significant duct leakage and deserves a line in the deficiency list.
What is the difference between preliminary and final readings?+
Preliminary readings are taken before any adjustment and show how the system was performing as installed. Final readings are taken after balancing and are the ones compared with design. Reports that include both let the reader see how much adjustment was needed, which says a lot about the quality of the installation.
Who signs an air balance report?+
On projects that require certification, the report is signed or stamped by the certified professional of record at the TAB firm, under the rules of the certifying body: a NEBB Certified Professional, an AABC Test and Balance Engineer, or a TABB-certified supervisor. The signature attests that the work followed that body's procedural standard.
How long should an air balance report be kept?+
For the life of the system. It is the baseline for every later comparison. When comfort complaints appear years on, or a space is renovated, the original report shows what each terminal was set to deliver and where the dampers were left.