Title 24 HVAC Compliance Guide
California regulates how buildings use energy through Title 24, Part 6. For anyone designing, installing, or replacing HVAC equipment in the state, that means paperwork at permit, tests in the field, and certificates before the permit closes. This guide explains how the pieces fit together under the 2025 Energy Code.
📝 Educational reference
What Title 24 Is
Title 24 of the California Code of Regulations is the state building code. It has twelve parts. Part 6 is the Building Energy Efficiency Standards, usually called the Energy Code. It is written by the California Energy Commission and updated on a three-year cycle.
The current edition is the 2025 Energy Code. It applies to buildings whose permit applications are submitted on or after January 1, 2026. Among other changes, it expands the use of heat pumps in new homes and renames the residential field verification program, as described in HERS to ECC.
Two other parts of Title 24 touch HVAC testing. Part 4 is the California Mechanical Code. Part 11 is the Green Building Standards Code, known as CALGreen, which is where the state's requirement to test, adjust, and balance new nonresidential systems is found.
Who Has to Comply
The Energy Code applies to newly constructed buildings, additions, and alterations to existing buildings. Replacing an air conditioner, furnace, heat pump, rooftop unit, or duct system is an alteration.
Requirements are organized by building type:
- Single-family residential
- Multifamily, with some requirements differing between buildings of three habitable stories or fewer and taller ones
- Nonresidential, including hotels and motels
There are exceptions. Systems serving healthcare facilities, for example, are exempt from the Energy Code's acceptance testing requirements because those facilities are regulated separately.
Compliance Paths
Every project must meet the mandatory measures, which are minimums that cannot be traded away. Beyond those there are two routes:
- Prescriptive. Follow a fixed list of requirements for each building component. Simple, with no flexibility.
- Performance. Model the building in approved software and show that its energy use is no higher than a standard design. This allows trade-offs, such as better windows in exchange for something else.
The path matters for testing. Some field verifications are mandatory for everyone. Others are required only when a feature is claimed for credit under the performance path.
The Document Chain
Compliance is demonstrated through a sequence of certificates, each signed by a different party at a different stage:
| Stage | Certificate | Nonresidential | Single-family | Signed by |
|---|---|---|---|---|
| Permit | Compliance | NRCC | CF1R | Designer or documentation author |
| Installation | Installation | NRCI | CF2R | Installing contractor |
| Testing | Acceptance | NRCA | — | Acceptance Test Technician |
| Verification | Verification | NRCV | CF3R | ECC-Rater |
The Certificate of Compliance is the important one to read early. It lists every acceptance test and field verification the project will need. If a test is not identified there, it tends to be discovered at final inspection, when it is most expensive. Title 24 Compliance Forms Explained covers each form family.
Two Testing Programs
The Energy Code relies on two separate programs to confirm that what was designed is what was built. They cover different buildings and are performed by people with different certifications.
| Acceptance testing | Field verification and diagnostic testing | |
|---|---|---|
| Applies to | Nonresidential buildings, hotels and motels, and multifamily buildings | Single-family homes, multifamily dwelling units, and some nonresidential measures |
| Performed by | Certified Acceptance Test Technician (ATT) | ECC-Rater, formerly HERS Rater |
| Certified by | An Acceptance Test Technician Certification Provider (ATTCP) | An ECC-Provider |
| Relationship to installer | May be the installing contractor's own technician | Independent third party |
| Record | Certificate of Acceptance (NRCA) | Certificate of Verification (CF3R or NRCV) |
Details are in Title 24 Mechanical Acceptance Tests, Acceptance Test Technician (ATT), and HERS to ECC.
What Gets Tested on HVAC
Nonresidential and multifamily buildings
Mechanical acceptance tests check that energy-related functions actually work: that the design outdoor airflow is delivered, that economizers open and close when they should, that demand control ventilation responds to CO₂, that variable-speed fans and pumps modulate, and that control sequences such as temperature resets and demand shed operate. The 2025 Energy Code has 23 mechanical acceptance forms. The Acceptance Test Finder lists the ones a given set of equipment usually triggers.
Homes
For ducted systems in single-family homes, the field verifications that come up most often are:
- Duct leakage, measured by pressurizing the ducts. See the Duct Leakage Calculator.
- System airflow, at least 350 CFM per ton of nominal cooling capacity for conventional systems.
- Fan efficacy, no more than 0.45 watts per CFM for gas furnace air handlers and 0.58 for other air handlers. See the Airflow and Fan Efficacy Checker.
- Refrigerant charge, for heat pumps in every climate zone and for air conditioners in climate zones 2 and 8 through 15.
- Ventilation airflow and kitchen range hood ratings for new dwelling units.
Title 24 HVAC Changeout Testing covers what applies when existing equipment is replaced.
Where Air Balancing Fits
Testing, adjusting, and balancing is not one of the Energy Code's acceptance tests, but the two are closely tied. An outdoor air acceptance test cannot pass on a system that has not been balanced, and CALGreen separately requires new nonresidential HVAC systems to be balanced to a recognized procedural standard. On most commercial projects the practical sequence is balancing first, then acceptance testing, then commissioning. Air Balancing vs. Title 24 Testing explains the differences and the overlap.
Official Sources
- 2025 Building Energy Efficiency Standards, California Energy Commission
- Acceptance Test Technician Certification Provider Program, California Energy Commission
- Energy Code Compliance (ECC) Program, California Energy Commission
- Energy Code Ace, forms, training, and reference tools funded by California utility customers