Title 24 Compliance Forms Explained
California's Energy Code is enforced through paperwork. Every requirement a project has to meet is declared on one certificate, confirmed on another, and verified on a third. Knowing which form does what, and who is responsible for it, is the easiest way to keep a project from stalling at final inspection.
📝 Educational reference
The Four Nonresidential Families
| Prefix | Certificate | When | Completed by | Purpose |
|---|---|---|---|---|
| NRCC | Certificate of Compliance | Permit application | Designer or documentation author | Shows the design meets the code. Lists required acceptance tests. |
| NRCI | Certificate of Installation | During and after installation | Installing contractor | Confirms what was installed matches the approved design. |
| NRCA | Certificate of Acceptance | Before final inspection | Acceptance Test Technician (mechanical and lighting); others for envelope and process | Records each acceptance test result. |
| NRCV | Certificate of Verification | Before final inspection | ECC-Rater | Records field verification of specific measures. |
Low-rise multifamily buildings, three habitable stories or fewer, use equivalent forms with the prefix LMCC for compliance. Their acceptance tests are still recorded on NRCA forms.
Reading a Form Number
Take 2025-NRCA-MCH-05-A:
- 2025 is the code cycle.
- NRCA is the family: Nonresidential Certificate of Acceptance.
- MCH is the system: mechanical. Other system codes include LTI and LTO for indoor and outdoor lighting, ENV for envelope, PRC for covered processes, and PLB for plumbing and water heating.
- 05 is the test number. MCH-05 is the economizer test.
- A is the completion method: by a certified Acceptance Test Technician through the certification provider.
The other suffixes: F forms are filled in directly, E forms are generated electronically by compliance software, and H forms are completed by an ECC-Rater.
Mechanical Forms Most Projects See
- NRCC-MCH-E. The mechanical Certificate of Compliance. Table O lists required acceptance tests. Read it at the start of the project.
- NRCI-MCH-E. The mechanical Certificate of Installation, plus specific installation forms such as NRCI-MCH-20-F for duct leakage, 22-F for fan efficacy, 23-F for airflow rate, and 25-F for refrigerant charge.
- NRCA-MCH-02-A through NRCA-MCH-24-A. The 23 mechanical acceptance tests, listed in Title 24 Mechanical Acceptance Tests.
- NRCA-PRC forms. Covered process tests, including kitchen exhaust (PRC-02), parking garage ventilation (PRC-03), laboratory exhaust (PRC-14), and fume hoods (PRC-15).
- NRCV-MCH forms. ECC-Rater verifications for enclosure air leakage, indoor air quality and mechanical ventilation, and local mechanical exhaust.
Residential Forms
- CF1R, Certificate of Compliance, at permit. Contains the ECC Feature Summary listing every verification required.
- CF2R, Certificate of Installation, completed by the installing contractor.
- CF3R, Certificate of Verification, completed by the ECC-Rater.
Residential certificates are registered in the ECC-Provider's data registry. Older cycles use the same form names with HERS terminology.
What the Building Department Checks
At plan check, staff review the Certificate of Compliance and the acceptance tests it identifies. At final inspection, the completed acceptance and verification certificates must be available before a certificate of occupancy is issued. Inspectors are advised to confirm that each Certificate of Acceptance carries an approved certification provider's logo and watermark, and that the technician's certification is current.
Where to Get Them
- 2025 Nonresidential Energy Code Forms, Energy Code Ace
- 2025 Building Energy Efficiency Standards, California Energy Commission