ABS

7 min read · Updated

Title 24 Compliance Forms Explained

California's Energy Code is enforced through paperwork. Every requirement a project has to meet is declared on one certificate, confirmed on another, and verified on a third. Knowing which form does what, and who is responsible for it, is the easiest way to keep a project from stalling at final inspection.

📝 Educational reference

Form names and numbers are those used for the 2025 Energy Code. Projects permitted under earlier code cycles use that cycle's forms.

The Four Nonresidential Families

Prefix Certificate When Completed by Purpose
NRCC Certificate of Compliance Permit application Designer or documentation author Shows the design meets the code. Lists required acceptance tests.
NRCI Certificate of Installation During and after installation Installing contractor Confirms what was installed matches the approved design.
NRCA Certificate of Acceptance Before final inspection Acceptance Test Technician (mechanical and lighting); others for envelope and process Records each acceptance test result.
NRCV Certificate of Verification Before final inspection ECC-Rater Records field verification of specific measures.

Low-rise multifamily buildings, three habitable stories or fewer, use equivalent forms with the prefix LMCC for compliance. Their acceptance tests are still recorded on NRCA forms.

Reading a Form Number

Take 2025-NRCA-MCH-05-A:

The other suffixes: F forms are filled in directly, E forms are generated electronically by compliance software, and H forms are completed by an ECC-Rater.

Mechanical Forms Most Projects See

Residential Forms

Residential certificates are registered in the ECC-Provider's data registry. Older cycles use the same form names with HERS terminology.

What the Building Department Checks

At plan check, staff review the Certificate of Compliance and the acceptance tests it identifies. At final inspection, the completed acceptance and verification certificates must be available before a certificate of occupancy is issued. Inspectors are advised to confirm that each Certificate of Acceptance carries an approved certification provider's logo and watermark, and that the technician's certification is current.

Where to Get Them

FAQ

What is an NRCC?+
A Nonresidential Certificate of Compliance. It documents that the design meets the Energy Code and is submitted with the permit application. For mechanical systems it is the NRCC-MCH-E, and its Table O lists the acceptance tests the project must pass. For the 2025 Energy Code, NRCCs are generated through approved software or the Energy Commission's online tools rather than paper forms.
What is the difference between an NRCA and an NRCV?+
An NRCA, Certificate of Acceptance, records an acceptance test performed by a certified Acceptance Test Technician on nonresidential or multifamily systems. An NRCV, Certificate of Verification, records field verification by an ECC-Rater, used for certain measures such as multifamily enclosure leakage and ventilation.
What do CF1R, CF2R, and CF3R mean?+
They are the residential equivalents. The CF1R is the Certificate of Compliance submitted at permit, the CF2R is the Certificate of Installation completed by the installer, and the CF3R is the Certificate of Verification completed by the ECC-Rater.
What do the letters at the end of a form number mean?+
They indicate how the form is completed. Forms ending in A are completed by a certified Acceptance Test Technician through the certification provider. Forms ending in F are downloaded and filled in directly. Forms ending in E are generated electronically by compliance software. Forms ending in H are completed by an ECC-Rater.
Where do I get the forms?+
Certificates of Compliance come from approved compliance software or the Energy Commission's online tools. Certificates of Acceptance ending in A are available only to certified technicians through their certification provider. Forms ending in F can be downloaded from the Energy Commission and from Energy Code Ace.