Title 24 Mechanical Acceptance Tests

A building can be designed to code and still waste energy if the economizer is wired backward or the outdoor air damper never opens. Mechanical acceptance testing is California's check against that. Before a nonresidential or multifamily project can close, a certified technician has to show, test by test, that the HVAC equipment and controls do what the Energy Code requires.

📝 Scope of this guide

This guide describes the mechanical acceptance tests under the 2025 Energy Code for educational purposes. The test procedures themselves are in Reference Nonresidential Appendix NA7, and the tests required for a specific project are the ones listed on its approved Certificate of Compliance.

What an Acceptance Test Is

Each acceptance test has two parts. The construction inspection confirms that the right equipment is installed, that sensors are located and calibrated correctly, and that required documentation is on site. The functional test puts the system through defined conditions and records how it responds: a signal is simulated, a setpoint is overridden, a damper is commanded, and the technician observes whether the result matches the acceptance criteria.

The outcome is pass or fail. A passing test is documented on a Certificate of Acceptance, form series NRCA. Mechanical tests are numbered NRCA-MCH-02 through NRCA-MCH-24.

When Testing Is Required

The Energy Code (Section 120.5) requires acceptance testing when regulated mechanical systems or controls are installed in:

The California Energy Commission's field sheet for building inspectors is direct on the last point: all HVAC replacements require acceptance testing, even when considered like-for-like. An existing, unaltered system that happens to serve a new addition is excepted. Systems serving healthcare facilities are exempt.

Which tests apply depends on what is installed. A single packaged rooftop unit with an economizer might need three or four. A central plant with variable flow pumping, a building automation system, and VAV air handlers can need a dozen or more. The Acceptance Test Finder gives a planning list from a checklist of equipment.

The 2025 Mechanical Acceptance Tests

Form Test What it confirms
NRCA-MCH-02-A Outdoor Air Outdoor airflow is measured and compared with the design minimum. On variable volume systems it is checked at both full and reduced supply airflow.
NRCA-MCH-03-A Constant Volume Single Zone HVAC Thermostat and unit controls behave correctly in occupied and unoccupied modes, including setback and outdoor air damper operation.
NRCA-MCH-04-A Duct Leakage Ductwork on qualifying single-zone systems is pressure tested and leakage compared with the allowed share of fan airflow.
NRCA-MCH-05-A Economizer, DOAS, HRV, ERV Economizer dampers modulate, the high-limit shutoff works, and operation is integrated with mechanical cooling. Covers dedicated outdoor air and heat recovery controls.
NRCA-MCH-06-A Demand Control Ventilation CO₂ sensors are correctly located and calibrated, and outdoor air responds as CO₂ rises above and falls below setpoint.
NRCA-MCH-07-A Supply Fan Variable Flow Controls The fan drive modulates to hold duct static pressure, and the static pressure reset operates.
NRCA-MCH-08-A Valve Leakage Test Isolation valves close fully when their chiller or boiler is off.
NRCA-MCH-09-A Water Temperature Reset Chilled or hot water supply temperature resets as programmed.
NRCA-MCH-10-A Hydronic System Variable Flow Control Pump speed and system flow respond as control valves open and close.
NRCA-MCH-11-A Automatic Demand Shed Control Zone setpoints shift on a demand response signal and return afterward.
NRCA-MCH-12-A FDD for Packaged Units The unit's fault detection and diagnostics report simulated faults.
NRCA-MCH-13-A FDD for AHU and Zone Terminal Units The control system detects and reports faults at air handlers and terminal units.
NRCA-MCH-14-A Distributed Energy Storage Storage-equipped DX systems charge and discharge on schedule.
NRCA-MCH-15-A Thermal Energy Storage Thermal storage systems charge and discharge on schedule.
NRCA-MCH-16-A Supply Air Temperature Reset Supply air temperature resets with load.
NRCA-MCH-17-A Condenser Water Temperature Reset Condenser water supply temperature resets as programmed.
NRCA-MCH-18-A EMS Acceptance The energy management control system is installed, programmed, and controlling what it is specified to control.
NRCA-MCH-19-A Occupied Standby Ventilation and setpoints respond when occupancy sensors show a zone is empty.
NRCA-MCH-20-A Multifamily Ventilation and Exhaust Dwelling unit ventilation and exhaust airflows are measured.
NRCA-MCH-21-A Multifamily Leakage Dwelling unit enclosure leakage is measured.
NRCA-MCH-22-A Duct Leakage Leakage of multifamily ventilation ductwork is measured.
NRCA-MCH-23-A HRV and ERV Heat and energy recovery ventilators are checked against airflow and fan efficacy requirements.
NRCA-MCH-24-A Cooling Tower Conductivity Controls Conductivity and blowdown controls operate as specified.

The "A" at the end of each form number means the test must be performed by a certified Acceptance Test Technician and recorded through that technician's certification provider. Acceptance forms for covered processes such as kitchen exhaust, laboratory exhaust, and parking garage ventilation carry the prefix NRCA-PRC and end in "F". Those may be completed by the builder, contractor, engineer, or commissioning agent.

The Tests That Come Up Most

Outdoor air (NRCA-MCH-02-A)

Nearly every project needs this one. The technician measures the outdoor airflow the system actually brings in and compares it with the design minimum on the compliance documents. The measured value has to fall within a set tolerance of design. On variable air volume systems the measurement is repeated with the supply fan at reduced flow, since a fixed damper position admits less outdoor air as the fan slows.

This is the test most dependent on air balancing. If the system has not been balanced and its minimum outdoor air position has not been set, there is nothing to verify.

Economizer (NRCA-MCH-05-A)

The technician simulates conditions that should enable and disable free cooling and watches the dampers. The outdoor air damper should open and the return damper close when the economizer is enabled, the high-limit control should lock the economizer out when outdoor air is too warm, and the unit should use economizer and mechanical cooling together when both are needed. Miswired actuators, missing sensors, and high-limit settings left at factory defaults are the familiar findings.

Demand control ventilation (NRCA-MCH-06-A)

Spaces with CO₂-based ventilation control are tested by exposing the sensor to a CO₂ concentration above setpoint and confirming that outdoor air increases, then to a lower concentration and confirming that it returns to minimum. Sensor location, height, and calibration documentation are part of the inspection.

Supply fan variable flow (NRCA-MCH-07-A)

On VAV systems the fan drive must modulate to maintain duct static pressure as terminal units open and close, and the static pressure setpoint must reset based on zone demand. The test drives the system to full and minimum flow and checks for stable control at both.

Who Performs the Tests

Only a certified Mechanical Acceptance Test Technician may perform tests on HVAC systems and controls. The technician must work for a certified Acceptance Test Employer, and both are certified by a provider approved by the California Energy Commission. The technician does not have to be independent of the installer. Many mechanical contractors employ their own. Acceptance Test Technician (ATT) explains the program and how to verify a certification.

Where Acceptance Testing Falls in the Schedule

  1. Permit. The Certificate of Compliance identifies the required tests. This is the moment to confirm the list is complete.
  2. Installation. The contractor completes the Certificate of Installation.
  3. Start-up, controls, and balancing. Equipment runs, controls are programmed, and airflows are set.
  4. Acceptance testing. The ATT performs each test and records it with the certification provider.
  5. Final inspection. The completed Certificates of Acceptance must be available to the enforcement agency before a certificate of occupancy is issued.

Inspectors are advised to check two things on each certificate: that it carries the logo and watermark of an approved certification provider, and that the technician's certification is current on that provider's website.

Preparing a Building to Pass

Most failed acceptance tests are not caused by defective equipment. They come from incomplete controls work and from tests scheduled before the system was ready.

Sources

FAQ

What is Title 24 mechanical acceptance testing?+
It is a set of field tests required by California's Energy Code to confirm that newly installed HVAC equipment and controls in nonresidential and multifamily buildings operate as the code requires. Each test combines a construction inspection with a functional test, and the result is recorded on a Certificate of Acceptance with a form number beginning NRCA-MCH.
Who can perform mechanical acceptance tests?+
Only a certified Mechanical Acceptance Test Technician (ATT), working for a certified Acceptance Test Employer. The California Energy Commission has required this for mechanical tests on nonresidential permit applications submitted since October 1, 2021. The technician may work for the installing contractor or for an independent firm.
Is acceptance testing required when replacing a rooftop unit?+
Yes. The Energy Commission's field guidance for building inspectors states that all HVAC replacements require acceptance testing, even when the replacement is considered like-for-like. The exceptions are narrow, covering certain electric resistance heaters of equal or lower capacity.
How do I know which tests my project needs?+
They are listed on the project's Certificate of Compliance: Table O of the NRCC-MCH-E for nonresidential buildings, or of the LMCC-MCH-01-E for low-rise multifamily buildings, and on the performance compliance form when that path is used. If the certificate does not list a test that the installed equipment clearly triggers, raise it early. The enforcement agency can still require it.
What happens if a test fails?+
The deficiency is corrected by the responsible trade, usually the mechanical or controls contractor, and the test is repeated. A Certificate of Acceptance is issued only for a passing test. Because the completed certificates must be available before a certificate of occupancy is issued, failures found late can hold up the whole project.
Are acceptance tests the same as commissioning?+
No. Acceptance tests are specific pass or fail checks defined in the Energy Code's Reference Appendices. Commissioning is a broader quality process covering design review, functional testing of full sequences, training, and documentation. The Energy Code requires both on larger nonresidential projects, and acceptance tests are usually treated as one part of the commissioning record.