Title 24 Mechanical Acceptance Tests
A building can be designed to code and still waste energy if the economizer is wired backward or the outdoor air damper never opens. Mechanical acceptance testing is California's check against that. Before a nonresidential or multifamily project can close, a certified technician has to show, test by test, that the HVAC equipment and controls do what the Energy Code requires.
📝 Scope of this guide
What an Acceptance Test Is
Each acceptance test has two parts. The construction inspection confirms that the right equipment is installed, that sensors are located and calibrated correctly, and that required documentation is on site. The functional test puts the system through defined conditions and records how it responds: a signal is simulated, a setpoint is overridden, a damper is commanded, and the technician observes whether the result matches the acceptance criteria.
The outcome is pass or fail. A passing test is documented on a Certificate of Acceptance, form series NRCA. Mechanical tests are numbered NRCA-MCH-02 through NRCA-MCH-24.
When Testing Is Required
The Energy Code (Section 120.5) requires acceptance testing when regulated mechanical systems or controls are installed in:
- Newly constructed nonresidential buildings, hotels and motels, and multifamily buildings
- Additions served by a new or replacement HVAC system
- Alterations, including equipment replacement
The California Energy Commission's field sheet for building inspectors is direct on the last point: all HVAC replacements require acceptance testing, even when considered like-for-like. An existing, unaltered system that happens to serve a new addition is excepted. Systems serving healthcare facilities are exempt.
Which tests apply depends on what is installed. A single packaged rooftop unit with an economizer might need three or four. A central plant with variable flow pumping, a building automation system, and VAV air handlers can need a dozen or more. The Acceptance Test Finder gives a planning list from a checklist of equipment.
The 2025 Mechanical Acceptance Tests
| Form | Test | What it confirms |
|---|---|---|
| NRCA-MCH-02-A | Outdoor Air | Outdoor airflow is measured and compared with the design minimum. On variable volume systems it is checked at both full and reduced supply airflow. |
| NRCA-MCH-03-A | Constant Volume Single Zone HVAC | Thermostat and unit controls behave correctly in occupied and unoccupied modes, including setback and outdoor air damper operation. |
| NRCA-MCH-04-A | Duct Leakage | Ductwork on qualifying single-zone systems is pressure tested and leakage compared with the allowed share of fan airflow. |
| NRCA-MCH-05-A | Economizer, DOAS, HRV, ERV | Economizer dampers modulate, the high-limit shutoff works, and operation is integrated with mechanical cooling. Covers dedicated outdoor air and heat recovery controls. |
| NRCA-MCH-06-A | Demand Control Ventilation | CO₂ sensors are correctly located and calibrated, and outdoor air responds as CO₂ rises above and falls below setpoint. |
| NRCA-MCH-07-A | Supply Fan Variable Flow Controls | The fan drive modulates to hold duct static pressure, and the static pressure reset operates. |
| NRCA-MCH-08-A | Valve Leakage Test | Isolation valves close fully when their chiller or boiler is off. |
| NRCA-MCH-09-A | Water Temperature Reset | Chilled or hot water supply temperature resets as programmed. |
| NRCA-MCH-10-A | Hydronic System Variable Flow Control | Pump speed and system flow respond as control valves open and close. |
| NRCA-MCH-11-A | Automatic Demand Shed Control | Zone setpoints shift on a demand response signal and return afterward. |
| NRCA-MCH-12-A | FDD for Packaged Units | The unit's fault detection and diagnostics report simulated faults. |
| NRCA-MCH-13-A | FDD for AHU and Zone Terminal Units | The control system detects and reports faults at air handlers and terminal units. |
| NRCA-MCH-14-A | Distributed Energy Storage | Storage-equipped DX systems charge and discharge on schedule. |
| NRCA-MCH-15-A | Thermal Energy Storage | Thermal storage systems charge and discharge on schedule. |
| NRCA-MCH-16-A | Supply Air Temperature Reset | Supply air temperature resets with load. |
| NRCA-MCH-17-A | Condenser Water Temperature Reset | Condenser water supply temperature resets as programmed. |
| NRCA-MCH-18-A | EMS Acceptance | The energy management control system is installed, programmed, and controlling what it is specified to control. |
| NRCA-MCH-19-A | Occupied Standby | Ventilation and setpoints respond when occupancy sensors show a zone is empty. |
| NRCA-MCH-20-A | Multifamily Ventilation and Exhaust | Dwelling unit ventilation and exhaust airflows are measured. |
| NRCA-MCH-21-A | Multifamily Leakage | Dwelling unit enclosure leakage is measured. |
| NRCA-MCH-22-A | Duct Leakage | Leakage of multifamily ventilation ductwork is measured. |
| NRCA-MCH-23-A | HRV and ERV | Heat and energy recovery ventilators are checked against airflow and fan efficacy requirements. |
| NRCA-MCH-24-A | Cooling Tower Conductivity Controls | Conductivity and blowdown controls operate as specified. |
The "A" at the end of each form number means the test must be performed by a certified Acceptance Test Technician and recorded through that technician's certification provider. Acceptance forms for covered processes such as kitchen exhaust, laboratory exhaust, and parking garage ventilation carry the prefix NRCA-PRC and end in "F". Those may be completed by the builder, contractor, engineer, or commissioning agent.
The Tests That Come Up Most
Outdoor air (NRCA-MCH-02-A)
Nearly every project needs this one. The technician measures the outdoor airflow the system actually brings in and compares it with the design minimum on the compliance documents. The measured value has to fall within a set tolerance of design. On variable air volume systems the measurement is repeated with the supply fan at reduced flow, since a fixed damper position admits less outdoor air as the fan slows.
This is the test most dependent on air balancing. If the system has not been balanced and its minimum outdoor air position has not been set, there is nothing to verify.
Economizer (NRCA-MCH-05-A)
The technician simulates conditions that should enable and disable free cooling and watches the dampers. The outdoor air damper should open and the return damper close when the economizer is enabled, the high-limit control should lock the economizer out when outdoor air is too warm, and the unit should use economizer and mechanical cooling together when both are needed. Miswired actuators, missing sensors, and high-limit settings left at factory defaults are the familiar findings.
Demand control ventilation (NRCA-MCH-06-A)
Spaces with CO₂-based ventilation control are tested by exposing the sensor to a CO₂ concentration above setpoint and confirming that outdoor air increases, then to a lower concentration and confirming that it returns to minimum. Sensor location, height, and calibration documentation are part of the inspection.
Supply fan variable flow (NRCA-MCH-07-A)
On VAV systems the fan drive must modulate to maintain duct static pressure as terminal units open and close, and the static pressure setpoint must reset based on zone demand. The test drives the system to full and minimum flow and checks for stable control at both.
Who Performs the Tests
Only a certified Mechanical Acceptance Test Technician may perform tests on HVAC systems and controls. The technician must work for a certified Acceptance Test Employer, and both are certified by a provider approved by the California Energy Commission. The technician does not have to be independent of the installer. Many mechanical contractors employ their own. Acceptance Test Technician (ATT) explains the program and how to verify a certification.
Where Acceptance Testing Falls in the Schedule
- Permit. The Certificate of Compliance identifies the required tests. This is the moment to confirm the list is complete.
- Installation. The contractor completes the Certificate of Installation.
- Start-up, controls, and balancing. Equipment runs, controls are programmed, and airflows are set.
- Acceptance testing. The ATT performs each test and records it with the certification provider.
- Final inspection. The completed Certificates of Acceptance must be available to the enforcement agency before a certificate of occupancy is issued.
Inspectors are advised to check two things on each certificate: that it carries the logo and watermark of an approved certification provider, and that the technician's certification is current on that provider's website.
Preparing a Building to Pass
- Controls programming is complete and sequences match the approved design, including setpoints that are often left at defaults: economizer high limits, CO₂ setpoints, static pressure and temperature resets.
- Sensors are installed where the documents show them, and calibration certificates are on hand.
- Air and water balancing is finished, and the balance report is available.
- Permanent power is on, and equipment has completed start-up.
- Someone who can operate the building automation system is on site during testing.
- Dampers and actuators have been stroked and are not blocked or disconnected.
Most failed acceptance tests are not caused by defective equipment. They come from incomplete controls work and from tests scheduled before the system was ready.
Sources
- Acceptance Test Technician Certification Provider Program, California Energy Commission
- 2025 Nonresidential Energy Code Forms, Energy Code Ace
- 2025 Building Inspector's Field Sheet: Acceptance Testing, California Energy Commission, docket 13-ATTCP-01