8 min read · Updated
Title 24 HVAC Changeout Testing
Replacing a worn-out air conditioner, furnace, or heat pump is the most common Title 24 project in California, and the one most often done without the required testing. This guide covers what the 2025 Energy Code requires when existing equipment is replaced, for homes and for commercial buildings.
📝 Educational reference
Why a Changeout Triggers Testing
A new high-efficiency unit connected to leaky, restrictive ductwork will not deliver its rated efficiency. The Energy Code treats equipment replacement as an alteration and requires the parts of the system that limit performance to be tested along with the new equipment. A permit is required, and the building department will not close it until the required certificates are registered.
Single-Family Homes
What counts as an altered system
Installing new heating or cooling equipment on an existing duct system, replacing the indoor or outdoor unit of a split system, and extending or modifying existing ductwork are all alterations. The Energy Commission is explicit that replacing just the outdoor unit, or just the indoor unit, of a split system triggers the duct sealing and verification requirements.
Duct leakage
The existing duct system is tested by the installer and then verified by an ECC-Rater. It passes by meeting one of three conditions:
- Total leakage of 10% or less of system air handler airflow
- Leakage to outside of 7% or less of system air handler airflow
- If neither is achievable, all accessible leaks sealed, confirmed by the rater through visual inspection and a smoke test
The Title 24 Duct Leakage Calculator converts a measured leakage in CFM into a percentage and checks it against these targets. Entirely new or complete replacement duct systems have their own, different target.
Refrigerant charge
When new equipment is installed, refrigerant charge verification applies to heat pumps in every climate zone and to air conditioners in climate zones 2 and 8 through 15. Under the 2025 Energy Code, weigh-in methods were revised and a fault indicator display alone may not be used to show compliance.
Airflow and fan efficacy
New systems must deliver at least 350 CFM per ton of nominal cooling capacity and stay within fan efficacy limits of 0.45 watts per CFM for gas furnace air handlers and 0.58 for other air handlers (Section 150.0(m)13). Altered systems have their own criteria in Section 150.2(b)1F, often tied to the refrigerant charge verification procedure. The Airflow and Fan Efficacy Checker applies the new-system limits.
Other mandatory items worth checking
- Filtration: MERV 13 or equivalent filters for systems with more than 10 feet of duct, in a two-inch-deep rack, or one inch if sized by the code's equation.
- Static pressure test point: ducted cooling systems need a hole for a static pressure probe, or a permanent probe, in the supply plenum.
- Heat pump controls: installer-adjustable defrost delays set to at least 90 minutes, and supplementary heat locked out above an outdoor temperature of no more than 35°F.
- Equipment sizing to the loads calculated under the code's referenced methods.
Who does what
- The contractor pulls the permit and registers the Certificate of Compliance (CF1R). For urgent replacements, it may be registered after work starts but before the permit is closed.
- The contractor installs the equipment, performs the required tests, and completes the Certificate of Installation (CF2R).
- An ECC-Rater performs the verifications and registers the Certificate of Verification (CF3R).
- The building department confirms the certificates at final inspection.
Commercial Buildings
Replacing a rooftop unit, split system, or air handler in a nonresidential building is also an alteration, but the verification route is different. The California Energy Commission's field sheet for building inspectors states that all HVAC replacements require acceptance testing, even when considered like-for-like. A typical packaged unit replacement triggers some combination of the outdoor air, single-zone controls, economizer, and fault detection tests, performed by a certified Mechanical Acceptance Test Technician. The Acceptance Test Finder builds a planning list, and Title 24 Mechanical Acceptance Tests explains each test.
Common Reasons Changeouts Fail
- Duct leakage far above the target because the old system was never sealed, discovered only after the new unit is installed
- Low airflow from undersized return ducts or restrictive filters, which no setting on the new unit can fix
- Refrigerant charge set by gauge readings at the wrong outdoor conditions
- No static pressure test point in the supply plenum
- Economizer or thermostat settings left at factory defaults on commercial units
Testing the existing ducts before the new equipment is chosen avoids most of these. The External Static Pressure Calculator is a quick way to see whether the existing ductwork can carry the new unit's airflow.
Sources
- 2025 Single-Family HVAC questions and answers, California Energy Commission
- 2025 Single-Family Residential Mandatory Requirements Summary, California Energy Commission
- 2025 Building Inspector's Field Sheet: Acceptance Testing, California Energy Commission